Work is to commence at once, and is to proceed with promptness and despatch.

Completion of work and delivery of building to Owner, to be six months after date of contract. Times of completion of the different parts to be as follows, the time allowed in each case to be from date of signing contract.

Foundation ready for sill:...................One month.

Frame enclosed and chimney completed......Two months.

Outside finish on..........................Three months and fifteen days.

Plastering...............................Four months.

Interior woodwork........................Five months and fifteen days.

Painter's work and completion..............Six months.

(Month and day to be inserted in contract and specification for each period mentioned above.)