192ft.0in. X 6ft. 7in. = l,264sq.ft. = 140sq.yds.,at$.40 $ 56.00

CESSPOOLS

Leaching Cesspool -

23 ft. 6 in. X 8 ft. 0 in. X 1 ft. 6 in. = 282 cu. ft. 25= 11 1/3 perches.

11 1/3 perches at $3.50...

.$39.65

Cover.....

. 2.50

42.15

Tight Cesspool -

11 ft. 6 in. X 8 ft. 0 in. = 92 sq. ft. X 15 bricks = 1,380 bricks.

1,380 bricks at $20.00 per M...

$27.60

Iron cover...

3.00

30.60

DRY WELLS

2 ft. 0 in. X 2 ft. 0 in. X 5 ft. 6 in. X 12 = 264 cu. ft. 25 = 11 perches

11 perches at $2.50.....

27.50

DRAINS

171ft. at $.20....

$34.20

14 bends at $.30....

. 4.20

38.40

Total cost of Stonework, Cesspools, and Drains

$754.15

Brickwork

Note. - Find the number of bricks in a foot of height in each chimney or pier, reckoning five courses to the foot of height.

Cellar -

35 x 8...

280

107 1/2 x 8...

860

55 x 8

440

Carried forward

1,580 bricks

Plastering Walls With Cement 0600391

Fig. 5.

Plastering Walls With Cement 0600392

Fig. 6.

Plastering Walls With Cement 0600393

Brought forward

1,580 bricks

Veranda Piers -

58!

X

10 ..

. 585

Chimneys -

107!

X

6 ft. 6 in..

. 700

105

X

11 ft. 0 in..

. 1,155

35

X

11 ft. 0 in..

. 385

35

X

4ft. 6in..

. 157

127 1/2

X

5 ft. 6 in..

. 701

35

X

19 ft. 0 in...

. 665

57 1/2

X

4ft. 0in...

. 230

127 1/2

X

11 ft. 0 in...

. 1,402

7,560 bricks

Summary -

7,560 bricks at $20.00per M., laid...

$ 151.20

3 fireplaces at $30.00 each...

90.00

Flue Linings -

26ft., 13 in. X 13 in., at $.35...

9.10

36ft, 9in. round, at $.30...

10.80

68ft,8 1/2 X 13,at$.30....

20.40

Total cost of Brickwork and Flue Linings,

$ 281.50

CONCRETING

Sq. Ft.

23 ft. 0 in.

X

38ft. 0in..

. 874

3 ft. 0 in.

X

9 ft. 6 in..

. 28!

15 ft. 0 in.

X

26 ft. 0 in..

. 390

4ft. 0in.

X

7 ft. 0 in..

28

1,320 sq. ft.

Total, 1,320 sq. ft. = 147 sq.yds., at $ 60 .......

. $88.20

Plastering

Note. - Take off square feet of plastered surfaces, and deduct one-half of the openings, after reducing to sq. yds.

Cellar -

Sq. Ft.

23 ft. 0 in.

X

. 874

9 ft. 6 in.

X

28

Carried forward

902 sq. ft.

Plastering 0600394

Fig. 8

Brought forward

902 sq. ft.

15 ft. 6 in.

X

26 ft. 0 in..

403

30 ft. 0 in.

X

8 ft. 0 in..

240

1,545 sq.ft.

First Story -

25 ft. 0 in.

X

40 ft. 0 in..

1,000

11 ft. 0 in.

X

3 ft. 0 in..

33

25 ft. 6 in.

X

16 ft. 6 in..

420

490 ft. 0 in.

X

9 ft. 0 in..

4,410

5,863 sq. ft.

Second Story -

Sq. Ft,

25 ft. 0 in

X

40 ft. 0 in..

1,000

16 ft. 6 in.

X

19 ft. 0 in..

313

520 ft. 0 in.

X

8 ft. 6 in..

4,420

5,733 sq. ft.

Total amount of plastered surfaces, 13,141 sq. ft.

Outs -

32 doors, average 40 sq. ft..

1,280

34 windows, average 15 sq. ft..

510

1,790 sq.ft.

1,790sq.ft. 2= 895sq.ft.

13,141 sq. ft. less 895 sq. ft. = 12,246 sq. ft. = 1,361 sq. yds.

Total cost of Plastering 1,361 sq. yds., at $. 40..

$ 544.40

CARPENTER WORK

Frame-

Ft. B. M

188 linear ft., 6

X

564

136 " " 4

X

6in. "..

272

74 " " 8

X

10 in. girders.

494

-

250 " " 4

X

500

188 " " 4

X

6 in. girts ..

376

2,206

$ 83.82

First-Story Frame, Bridging and Under Floor 25 ft. 0 in. X 40 ft. 0 in..

. 1,000

Carried forward

$ 83.82

Plastering 0600395

Fig. 9.

Plastering 0600396

Fig 10.

Brouqht forward

$ 83.82

11 ft. 0 in.

X

3 ft 0 in..

33

26 ft. 0 in.

X

16 ft. 6 in..

429

1,462 sq.ft.

1,462 sq.ft. = 14.62 squares, at $9.35 per square .....

. $ 136.70

Upper Floor -

Hard Pine

25 ft. 6 in.

X

16 ft. 6 in. =

421 sq.ft., at $10.50

per square....

$ 44.21

Oak

25 ft. 0 in.

X

40 ft. 0 in.

= 1,000 sq.ft.

11 ft. 0 in.

X

3 ft. 0 in.

33 "

1,033 sq. ft.

1,033 sq. ft. at $20.00 per square..

. $ 206.60

Porch FLOOR -

6 ft. 0 in.

x

11 ft. 0 in.

-

66 sq. ft.

9 ft. 0 in.

X

5 ft. 0 in.

=

45 "

Piazza Floor -

26 ft. 0 in.

X

9 ft. 0 in.

=

234 "

20 ft. 6 in.

X

7 ft. 0 in.

=

144 "

489 sq. ft.

489 sq. ft. at $12.35 per square..

$ 60.39

Second-Story Frame. Bridging and Strapping Floors -

40 ft. 0 in.

X

25 ft. 0 in.

. 1,000 sq.ft.

20 ft. 0 in.

X

17 ft. 0 in.

. 340 " "

1,340 sq.ft.

1,340 sq. ft. at $18.00 per square..

$ 241.20

Third Story -

1,340 sq. ft. at $10.10 per square..

$ 135.34

Roof Frame, Boarding and Shingles-

30 ft. 0 in.

X

16 ft. 6 in.

X

2 sides. .

990 sq. ft.

34 ft. 0 in.

X

16 ft. 6 in.

X

2 sides. .

1,122 " "

2,112 sq.ft.

2,112 sq. ft. at $16.67 per square..

$ 352.07

Flashing......

$ 40.00

Tin Roof, Frame and Boarding-

21 ft. 0 in.

x

7 ft. 6 in..

157 sq. ft.

Carried forward

$1,300.33

Plastering 0600397

Fig. 11.

Brought forward

$1,300.33

19ft. 0in. X 6ft. 6in..

124 sq. ft.

11 ft. 0 in. X 5 ft. 6 in..

60 " "

14ft. 0in. X 9ft. 6in..

133 " "

474 sq.ft.

474 sq. ft. at $20.92 per square..

$ 99.16

Outside Walls, Studding and Boarding -

172ft. 0in. X20ft0in..

3,440 sq. ft.

6 ft. 6 in. X 10 ft. 0 in. X 2 sides

130 " "

3 ft. 0 in. X 9 ft. 0 in. X 2 sides

54 " "

3,624 sq.ft.

3,624 sq. ft. at $8.30 per square

$ 300.79

Inside Studding -

180ft. 0in. X 9ft. 0in..

1,620 sq.ft.

196ft. 0in. X 8ft. 6 in..

1,666 " "

28 ft. 0 in. X 8ft. 0in..

224 " "

3, 510 sq. ft.

3,510 sq. ft., at $4.00 per square

$ 140.40

Clapboarding -

44 ft. 0 in. X 19 ft. 0 in. X 2 sides.

1,672 sq.ft.

6ft. 0in. X 8ft. 0in. X 2sides.

96 " "

2 ft. 0 in. X 9 ft. 0 in. X 2 sides.

36 " "

39 ft. 0 in. X 19 ft. 0 in. X 2 sides.

1,482 " "

3,286 sq. ft.

3,286 sq. ft. at $7.95 per square. .

$261.23

Deduct for stock only, 36 windows = 540 sq. ft., at $4.70 per square

25.38

$ 235.85

MISCELLANEOUS

Dormers -

6, at $50 each....

$ 300.00

Main Cornice -

180 ft., at $1.25 per ft...

225.00

Balustrade on Roof -

96 ft, at $0.50 per ft..

$48.00

18 posts, at $1.50 each..

27.00

75.00

Carried forward

$2,676.53

Piazza Finish -

Brought forward

$2,076.53

Cornice -

102 ft., at $2.00 per ft..

204.00

Columns -

9 in place, at $10.00 each..

90.00

Corner Pilasters -

2 1/2 in place, at $8.00 each. ..

20.00

Balustrade -

76 ft., at $.50 per ft.

. $38.00

Small Posts -

8 1/2, at $1.00 each.

. 12.00

50.00

25.00

Lattice -

55 ft. 0 in. X 1 ft. 6 in. = 82 1/2 sq. ft, at $.15

12.37

Porch Ceiling -

111 sq. ft., at $10.00 per square..

11.10

25.00

Corner Boards -

252 ft. 0 in. X 8 in. = 168 sq. ft., at $.30 per sq. ft.

50.40

Water Table -

117 1/2 linear ft., at $.20 per ft...

23.50

Windows and Frames -

Attic -

4 windows, circular top, at.

$11.20 each

$ 44.80

$5.25 each

21.00

Second Story -

8 windows, 3 ft. 6 in.

X

5 ft. 0in., at

$13.33 each

$106.64

7 windows, 2 ft. 6 in.

X

4ft. 6in., at

$11.44 each

80.08

First Story -

1 window, 2 ft. 6 in.

X

4ft. 6 in..

$ 11.44

2 windows, 2 ft. 6 in.

X

5 ft. 6 in., at

$12.00 each

24.00

2 windows, 2 ft. 6 in.

X

3 ft. 9 in., at

$11.00 each

22.00

2 pairs French windows (oak),

4 ft. 6 in.

X

7 ft. 6 in., at

$18.24 each

36.48

1 window, 3 ft. 4 in.

X

5 ft. 6 in. (oak finish)-----

16.57

Carried forward

$3,550.91

Plastering 0600398

Fig. 12.

Brought forward

$3,550.91

1 window, 3 ft. 4 in. X 5 ft. 6 in. (birch finish) .

10.57

1 window, 2 ft. 6 in. X 5 ft. 6 in. (birch finish) .

14.45

2 windows, 3 ft. 4 in. X 5 ft. 5 in. (whitewood), at

........$13.33 each

26. 66

4 windows, 2 ft. 6 in. X 4 ft. 6 in. (N. C. pine), at

.......$11.44 each

45.76

Front Door, with side and top lights -

3 ft. 3 in. X 7 ft. 6 in...

56.33

Rear Door -

2 ft. 10 in. X 7 ft. 6 in...

13.46

Cellar Sashes -

12, at $3.25 each....

30.00

Inside Finish -

Coal bins in basement, 240 sq. ft.

Studding 240 sq. ft. at $3.00 per square:

$ 7.20

Boarding 240 " "$4.75 " "

11.40

Labor on 2 door, one day...

3.25

21.85

Cold-Air Box -

3 ft. 0 in. X 1 ft. 0 in., 25 ft. long, at $.62 per linear ft. .

15.50

Basement Partitions -

46 ft. 0 in. X 8 ft. 0 in., 368 sq. ft., at $8.75 per square. .

32.20

3 doors, at $8.87 each...

26.61

671/2 ft. shelving, at $.15 per ft...

10.12

1 door to bulkhead....

10.00

First Story -

1 door, 2 ft. 8 in. X 7 ft. 6 in. (whitewood and birch finish)

20.67

1 pair sliding doors (whitewood and birch finish) .

53.52

40 ft. birch base at $.20 per ft....

8.00

1 door, 3 ft. 3 in. X 7 ft. 6 in. (whitewood and oak) .

. 22.67

1 door, 2 ft. 10 in. X 7 ft. 6 in. (whitewood and oak) .

. 20.67

Wood Cornice in Dining Room -

56 ft, 6 in. X 6 in. (birch), at $.48 per ft. .

$26.88

56 ft. picture moulding, at $.06 per ft.

. 3.36

30.24

Wood Cornice in Library -

82 ft., 6 in. X 6 in. (oak), at $.48 per ft.

. .839.36

Carried forward

$39.36

$4,035.19

Brought forward

$39.36

$4,035.19

82 ft. picture moulding, at $.06 per ft.

. 4.92

44.28

Oak Base -

72 ft. at $.20 per ft....

. 14.40

1 door, 3 ft. 0 in. X 7 ft. 6 in (whitewood)..

12.59

Vestibule Door, side lights and top light, same as front door

56.33

Whitewood Base, 101 ft., at $.10 per ft..

. 10.10

5doors (N. C. pine), at 89.48each...

. 47.40

CHINA CLOSET FINISH....

. 100.00

PANTRY....

. 50.00

Kitchen and Back Entry Sheathing -

65 linear ft., at $.40 per ft....

26.00

Mantels -

Allowance ....

.$125.00

Labor of setting....

. 6.50

$131.50

Second Story -

16 doors stock, at $9.48 each...

.$151.68

1 arch in hall....

. 10.00

2 wood columns, at $10.00 each...

. 20.00

5 closets, at $3.50 each...

. 17.50

1 linen closet...

. 25.00

1 linen closet...

. 20.00

Third Story -

2 doors, finished one side, at $7.04 each..

$ 14.08

1 closet door.....

7.04

Tank......

. 10.00

Finished floor, 100 sq. ft....

7.25

Base, 14 ft., at $.10 per ft....

1.40

Conductors -

120 ft, at $.13 per ft, put up..

515.60

6 goosenecks, at $1.00 each...

6.00

$ 21.60

Cutting and Fitting for Plumbing and Heating.

35.00

Freight, Fares and Expenses...

50.00

Insurance......

10.00

Total cost of Carpenter Work. ..

$4,928.34

Plastering 0600399

Fig. 16

STAIRS

Front Stairs -

128 ft. spruce, at $30 per M...

3.84

120 ft. whitewood, at $70 per M..

8.40

85 ft. quartered oak, at $150 per M.

12.75

30 ft. mahogany rail and turn ..

24.00

5 paneled posts at $5.00 each ..

25.00

105 balusters at $.15 each...

15.75

11 nosings at $.06 each...

.66

25 scotias at $.03 each...

.75

-

Nails, glue, etc....

1.00

Labor.....

56.00

$148.15

Back Stairs -

First Flight -

55 ft. spruce, at $30 per M...

$ 1.65

105 ft. N.C. pine, at $60 per M ..

6.30

16 scotias at $.03 each...

.48

Nails, etc....

.75

Labor.....

16.00

25.18

Second Flight -

54 ft. spruce, at $30 per M. ...

$ 1.62

110ft. N. C. pine, at $60 per M..

6.60

17 scotias at $.03 each...

.51

Nails etc....

.75

1 post....

.75

4 ft. rail, at $.m per ft...

.50

12 balusters at $.06 1/4 each..

.75

Labor....

17.00

28.48

Cellar Stairs -

40 ft. spruce, at $30 per M...

$ 1.20

75ft.N. C.pine,at$60perM..

4.50

Post.....

.50

Rail.....

1.20

Labor ....

5.00

12.40

$214.21

Framing....

. 2.00

Total cost of Stairs...

$216.21

Hardware

Note. - This estimate is based upon a fair quality of hardware, the butts being of bronze plated steel, the knobs of struck-up bronze metal, with rose and escutcheon combined; the sash fasts of solid bronze metal, also lifts and catches.

BASEMENT

Bulkhead, Outside -

2 pairs extra heavy galv. T hinges, 8-inch at $.85 each....

$1.70

2 hooks and staples, 5 inch, at.

.$. 10 each

.20

Labor.....

1.00

Bulkhead, Inside -

1 pair heavy T hinges, 8-inch...

.15

1 thumb-latch....

.10

Labor....

.50

Three Doors -

3 pairs butts, 3 1/2 X 3 1/2-inch, at.

.$.15 each

.45

3 sets locks at...

.$.45 each

1.35

Labor....

1.50

Hinged Windows -

12 pairs butts, 1 1/4-inch, at..

. $.06each

.72

12 hooks and eyes, at . ..

.$.02 each

.24

12 buttons, at....

.$.02 each

.24

Labor....

1.50

$ 9.65

FIRST FLOOR

Entrance Door -

1 1/2 pairs butts, 4 1/2-inch, at..

.$.38 each

$ .57

1 set lock, bronze metal...

9.50

Labor....

2.00

Seven Inside Doors, Front -

7 pairs butts, 3 1/2 X 3 1/2-inch, at.

$.30 each

2.10

7 sets locks at....

$1.00 each

7.00

Labor...

5.25

Carried forward

$26.42

$9.65

Hardware 0600400

Fig. 14.

Brought forward

$26.42

$9.65

Side Entrance Door -

1 1/2 pairs butts, 4 1/2 x 4 1/2-inch, at..

$. 38 each

.57

1 set locks...

2.25

Labor...

1.00

One Pair Sliding Doors, 5 ft. 0 in. -

1 set bangers, 5 ft. 0 in, Double ..

3.50

1 set S. D. locks...

2.50

Labor....

2.00

Six Inside Back Portions -

6 sets lock sat...

$.45 each

2.70

6 pairs butts, 3 1/2 x 3 1/2-inch at..

$. 15 each

.90

Labor...

4.00

Back Doors -

1 1/2 pairs butts, 4 1/2 X 4 1/2-inch, at.

$.20 each

.30

1 set locks....

2.25

Labor.....

1.00

Ice-Chest Door -

1 pair butts, 3 X 3-inch...

.40

1 IH lever, galvanized...

.60

1 brass hasp and padlock...

1.50

Labor...

.50

China Closet -

2 pairs glass doors -

2 pairs butts, 2 1/2 X 2 1/2-inch, at.

$.26 each

.52

2 elbow catches, at...

$.06 each

.12

2 cupboard catches, at...

$.15 each

.30

1 pair cupboard doors -

2 pairs butts, 2 1/2 x 2 1/2-inch, at..

$.10 each

.20

1 elbow catch...

.06

1 cupboard catch...

.15

20 drawer-pulls, at..

$.06 each

1.20

Labor...

2.50

Pantry -

4 cupboard doors -

4 pairs butts, 2 1/5 x 2 1/2-inch, at.

$.10 each

.40

Carried forward

$57.84

$9.65

Brought forward

$57.84

$9.65

4 cupboard catches at...

.60

1 bbl. swing...

.75

10 drawer-pulls, at..

.$.06 each

.60

Labor...

2.00

Windows -

15 sash fasts, at...

.$. 30 each

4.50

30 sash lifts, at...

$. 60 each

1.80

Labor...

7.50

Casement Windows,

4 pairs butts, 3 X 3-inch, at.

.$. 50 each

2.00

2 pairs flush bolts, at..

.$1.00 each

2.00

2 casement fasts, at..

.$. 45 each

.90

Labor...

1.00

$81.49

SECOND FLOOR

Sixteen Doors -

16 pairs butts, 3 1/2 X 3 1/2-inch, at .

$.30 each

$ 4.80

16 sets locks, at...

$. 90 each

14.40

Labor....

.10.40

Windows -

14 sash fasts, at...

$. 30 each

4.20

1 sash fast...

.35

28 sash lifts, at...

.$.06 each

1.68

2 sash lifts, at...

.$.10 each

.20

Labor..

7.00

Six Drawers in Linen Closet -

12 drawer-pulls, at..

.$.06 each

.72

Labor...

.25

$44.00

Bathroom -

1 pair butts, 3 1/2 x 3 1/2-inch (nickel-plate)..

.40

1 set locks (nickel-plate)...

1.25

Labor...

.75

$ 2.40

ATTIC

Two Doors -

2 pairs butts, 3 1/2 X 3 1/2 inch, at

$.12 each.

.$.24

2 sets locks, at..

$.45each.

. .90

Labor...

.1.00

Carried forward

$2.14

$137.54

Hardware 0600401

Fig. 15.

Hardware 0600402

Fig. 16.

Brought forward

$2.14

$137.54

Two Low Doors -

2 pairs butts, 2 1/2 X 2 1/2-inch, at

.$.10 each.

. .20

2 cupboard turns, at .

$ 35 each

. .70

Labor...

1.00

Windows -

8 sash fasts, at...

.$.30 each.

.2.40

16 sash lifts, at..

.$.06 each.

. .96

Labor....

.4.00

6 doz. H. & C. hooks, 639 1/2, at

.$.50 doz

.3.00

3 doz. base knobs, at.

.$.35 doz

.1.05

Labor...

.2.50

$ 17.95

Total cost of Hardware put on..

$155.49

HEATING

Furnace -

1 No. 28 Crawford furnace (28-in. firepot) . .

$125.00

22 ft. 8-in. galv. iron smoke-pipe, 55 lbs., at....$.09 lb.

4.95

Registers -

1 14 X 18-in. register, stone, box and netting,

4.72

4 9 X 12-in. registers, stone, box and netting at....$1.57 each

6.28

4 8 X 10-in. registers, stone, box and netting at....$1.19 each

4.76

4 8 X 10-in. registers, stone, box and netting, at....$1.15 each

4.60

Piping, including dampers, collars, and elbows -

12 ft. 14-in. tin pipe, at.

$.27 per ft.

3.24

64ft.9-in. " " at.

$.16 " "

10.24

278ft.7-in. " " at.

$.10 " ".

27.80

Covering for Risers (6 lbs. asbestos paper per pipe)-

5 risers, 30 lbs., at $.05 lb ..

1.50

Plastering Rings in Cellar -

For 13 pipes at $.20 each..

2.60

$ 195.69

Office expense and profit...

48.92

$244.61

Carried forward

$244.01

Hardware 0600403

Fig. 17,

Brought forward

$244.6l

Labor -

Measuring and laying out risers, man 1 day .

$4.80

Erecting risers, man 2 days, helper 1 day. . .

12.00

Laying out and erecting cellar pipes and furnace, man 3 days, helper 2 days.

19.20

Finishing, man 1 day ..

4.80

Carting and expenses ...

10.00

50.80

Total cost of Heating Apparatus..

$ 295.41

PLUMBING

Waste and Soil Pipes -

2 4-in. lead bends, at $1.10 each..

$2.20

2 4-in. sleeves, at $.65 each..

1.30

5 2-in. " at $.28each ..

1.40

2 3 X 2-in. sleeves, at $. 45 each..

.90

1 1 1/2-in. Pemberton trap...

6.80

30 lbs. solder, wiping, at $.25 lb..

7.50

2 trap plugs, at $.42 each ..

.84

2 6-in. traps, at $2.35 each..

4.70

1 6-in. cesspool ...

3.00

4 1 1/2-inch solder nipples, at $. 15 each.

.60

1 4-in. roof flashing....

1.35

Soil pipe...

47.87

15 ft. 1 1/2-in. lead pipe, No. 55..

3.24

50 ft. 2-in. iron pipe

8.96

40ft.lf.in. " "

Soil fittings, 1/3 cost of pipe....

15.96

Cast-iron fittings, 20 per cent...

1.79

$ 108.41

Miscellaneous Fittings -

3 4-in. brass C.O..

$ 2.70

1 5-in. brass C.O..

1.50

Refrigerator waste...

12.50

Local vents...

12.00

1 ball-cock...

1.25

2 sill cocks...

2.00

Tank overflow...

6.50

4 3/4-inch S. & W. cocks...

3.24

Carried forward

$41.69

$108.41

Brought forward

$ 41.69

$ 108.41

1 boiler valve and chain...

.70

25 lbs. tinned copper, at $.32 lb..

8.00

6 3-part hangers, brass...

6.30

2 3/4-in. hose bibs...

1.50

3 3/4-inch plain bibs...

2.10

Street connections...

55.00

1 lb. putty....

.05

2 lbs. grafting wax...

.50

Calking lead, 380 lbs...

22.80

Oakum....

1.60

$ 140.24

Fixtures -

1 36 x 24 x 8-in. sink, 12-in. back..

$11.40

1 24 x 14-in. pantry sink...

14.00

1 pair pantry cocks...

3.60

2 24 x 48-in. trays, 12-in. back..

14.10

15-ft. bathtub, complete...

41.00

1 lavatory, complete...

32.50

1 water-closet, complete..

60.00

1 40-gallon boiler...

16.75

1 " " " stand...

.85

12 lbs. fine solder...

3.12

Clamps and hooks...

2.70

Tinned tacks....

.15

Fuel.....

1.95

$ 202.12

Supplies and Labor -

126 ft. 3/4-inch galv. water pipe..

$4.41

22ft. finch " " " ..

.62

Fittings, 1/3 cost of pipe...

1.67

74 ft. 3/4-in. brass..

$23.49

56ft. 1/2 in- " ..

16.24

39.73

Fittings, 20 per cent...

7.95

Painting of iron pipes...

9.75

Stop-cocks...

3.54

Sink and tray legs...

4.72

Lead, oil, etc...

.65

Carried forward

$ 73.04

$ 450.77

Brought forward

$ 73.04

$ 450.77

Clamping brass and screws.

.25

Cartage and fares..

5.00

Labor, 40 days, at $6.00 per day . .

240.00

318.29

$ 769.06

Profit, 10 per cent..

76.90

Total cost of Plumbing..

$ 845.96

ELECTRIC WIRING

75 ft.

No. 4 S.B.R.C.wire..

$ 4.80

150 ft.

No. 1 S. B. R. C. wire.

4.26

40

Large porcelain tubes, 5 cents. .

2.00

30

,, ,, knobs, 5 cents . ...

1.50

1

3-pole 50-amp. fused switch...

1.50

1

Main cabinet (meter).....

3.50

1

8-circuit cut-out panel....

16.00

2,500 ft.

No. 14 S.B.R.C.wire....

28.60

500 ft.

1 4-in. circular loom....

20.00

800

5 1/2 knobs.....

3.20

1,600

5-in. porcelain tubes....

4.00

100

Fire stops.....

9.00

100

12-in. porcelain tubes....

10.00

18

Ceiling boxes....

1.80

30

Bracket boxes...

3.00

11

Switch boxes....

2.20

11

,, ,, ....

. 12.10

Labor on No. 14 wire...

55.00

,, ,, mains...

15.00

,, ,, finish...

. 15.00

Teaming and freight...

5.00

Sundries....

5.00

Nails, leatherheads, etc...

3.00

$ 225.46

Office expense, 10 per cent....

22.55

$ 248.01

Profit, 20 per cent...

. 49.60

Total cost of Electric Wiring..

.$ 297.61

Note. - This estimate is figured on outlet boxes at all outlets; and includes a main cabinet and main switch to connect with the meter and to cover the meter, on an eight-circuit panel-board, which allows one spare circuit. The panel-board is to be made of slate, with slate gutters and linings, with good wood door and trim.

The labor is estimated on wages being $3.60 per day for a journeyman, and $2.00 per day for helper. This price is above that paid in small places, but is below what is paid in some cities.