This section is from the book "A Treatise On Architecture And Building Construction Vol4: Plumbing And Gas-Fitting, Heating And Ventilation, Painting And Decorating, Estimating And Calculating Quantities", by The Colliery Engineer Co. Also available from Amazon: A Treatise On Architecture And Building Construction.
The walls between base sill and water-table are faced with ashlar, which extends around main walls to porches, and all porch piers are built of ashlar.
Sq. Ft. | |
Facing for cellar walls, 78 lineal ft. X 2 ft. 3 in.... | 175.5 |
Porch piers, 29 1/4 lineal ft. X 2 ft. 3 in........ | 65.8 |
241.3 |
Cost.
The estimated cost of ashlar is based on the following analysis:
Cost of 1 Square Foot of Ashlar. | |
Cost of stone,bluestone facing............ | $0.30 |
Hauling stone, say 1/10 of cost of stone........ | .03 |
Mortar............ | .01 |
Labor, estimating 80 sq. ft. per day for 2 masons and 1 laborer: | |
2 masons, at $3 per day........ | .075 |
1 laborer, at $1.50 per day........ | .02 |
Cost per square foot.................... | $0.44 |
Summary.
From the foregoing quantities, the ashlar amounts to 241.3 square feet, which, at 44 cents per square foot, will make the total cost of ashlar. $106.17
Cost per Ft. | Total Cost. | |
Base, or ground sill, extendingunder porches (except under stone steps) and along exposed main walls, 172 ft., 5" x ll" and 6"x 8" dressed and chamfered sandstone.......... | ||
$0.60 | $103.20 | |
Water-table, extending around main walls, 178 ft. 6 in., 6" X 10" dressed and chamfered sandstone....... | ||
.60 | 107.10 | |
Lintel course, extending over brick walls, 125 lineal ft, 6"X 10" dressed sandstone............ | ||
.60 | 75.00 | |
12 dressed sandstone window sills, cut with lug and drip, 5"x 8", 55f lineal ft................. | ||
.60 | 33.45 |
Cost per Ft. | Total Cost. | |
Cut-stone jambs for main door, 10" X 10", 19 1/2 lineal ft............ | $1.75 | $34.13 |
1 door sill, 6" X 10", 5 3/4 lineal ft..... | 1.00 | 5.75 |
Coping on area walls, 3"x l6", 12 lineal ft................ | .60 | 7.20 |
Porch steps, 8" X 12", 57 lineal ft., dressed sandstone.............. | 1.25 | 71.25 |
9 bluestone steps, for outside cellar entrance, 4' X 12" X 2"........ | .25 | 9.00 |
Bluestone lintel for kitchen fireplace, 6' X 12" X 6"............ | 1.00 | 6.00 |
Cut stone for main chimney.......... | 15.00 | |
Labor, setting lintels, sills, etc.: 1 mason, 8 days, at $3.00 per day... | 24.00 | |
2 laborers, 8 days each, at $1.50 per day. | 24.00 | |
Total cost of cut stone............... | $515.08 |
CONCRETE FOOTINGS AND FLOOR. | |||
Quantities. | |||
Footings, as per "Excavation for Footings," 486.7 cu. ft. ÷ 27....... | 18.3 cu. yd. | ||
Concrete floor: | Sq. Ft. | ||
Area of cellar excavation....... | 1,740.2 | ||
Deduct area of footings......... | 584.3 | ||
1,155.9 | |||
Add for 6-inch strip over inner projection of wall footings, 165' x 6".......... | 82.5 | ||
Add for projection on both sides of interior walls, 79' X 6"... | 38.5 | ||
Add for projection over chimney-footing, 31' 6"....... | 15.5 | • | |
Total area of concrete floor, | 1,292.4 | = | 143.6 sq. yd. |
Cost.
The estimates for concrete footings and floor are based on the following analyses of costs:
Cost of 1 Cubic Yard of Concrete. | |
1 barrel of Rosendale cement........ | $1.25 |
3 barrels of sand, or 1/3 load, at $1.50 per load.... | .50 |
1 cu. yd. (about 6 barrels) of broken stone..... | 1.50 |
Mason, 1/4 day, at $2.50.......... | .62 |
Laborer, 1 day, at $1.50............. | 1.50 |
Total................... | $5.37 |
Cost of 1 Square Yard of Cellar Floor. | |
Concrete, 4 1/2 inches thick, at $5.37 per cubic yard.. | $0.67 |
Sand bed, 6 inches thick, approximately 1 barrel.. | .17 |
Spreading sand............. | .03 |
1/ 12 barrel of Portland cement for 1/2-inch finishing coat, at $2.60 per barrel............... | |
.21 | |
1/12 barrel of white sand, at $1.00 per barrel..... | .08 |
Mixing and speading surface layer............ | .08 |
Cost per square yard.............. | $1.24 |
Summary. | |
Footing concrete, as per foregoing figures, 18.3 cu. yd. at $5.37 per cu. yd......... | |
$98.27 | |
Concrete floor, 143.6 sq. yd. at $1.24 per sq. yd. . | 178.06 |
Total cost of concrete............ | $276.33 |
RECAPITULATION OF COST OF STONEWORK. | |
Rubble masonry...... | $416.83 |
Ashlar masonry....... | 106.17 |
Cut stone......... | 515.08 |
Concrete footings and floor....... | 276.33 |
Total cost of stonework............. | $1,314.41 |
 