The Contractor shall, between the first and seventh of each month, deliver to the Architect a statement, sworn to if required, showing in detail and as completely as possible all moneys paid out by him on account of the cost of the work during the previous month for which he is to be reimbursed under Article 5 hereof, with original pay rolls for labor, checked and approved by a person satisfactory to the Architect, and all receipted bills.

He shall at the same time submit to the Architect a complete statement of all moneys properly due for materials or on account of separate contracts, or on account of his fee, or otherwise, which are to be paid direct by the Owner under Article 7 hereof.

The provisions of this Article supersede those of Article 26 of the General Conditions of the Contract.