This section is from the book "The Building Trades Pocketbook", by International Correspondence Schools. Also available from Amazon: Building Trades Pocketbook: a Handy Manual of reference on Building Construction.
The following proportions and cost of materials, and amount of labor required for the classes of work below specified, are reasonably accurate, and will serve to give a good idea of how to estimate such work.
1 perch stone (25 cu. ft.) delivered at work...................... | $1.25 |
1 bu. lime........................................................ | .25 |
1/6 load of sand, at $1.50 per load........................................ | .25 |
1/3. day mason's labor, at $2.50 per day............................... | .83 |
i day helper's labor, at $1.50 per day................................ | .38 |
Total............................................................................ | $2.96 |
Using 1-to-S Portland Cement Mortar. | |
1 perch stone (25 cu.ft) delivered at work....................... | $1.25 |
1/2 bbl. Portland cement, at $2.60 per bbl........................... | 1.30 |
1/6 load of sand, at $1.50 per load.................. | .25 |
1/3 day mason's labor, at $2.50 per day................................ | .83 |
1/4 day helper's labor, at $1.50 per day............................... | .38 |
Total............................................................................ | $4.01 |
Using l-to-3 Rosendale Cement Mortar. | |
1 perch stone...................................................................... | $1.25 |
1/2 bbl. Rosendale cement, at $1.25 per bbl........................ | .63 |
1/6 load sand, at 81.50 per load............................................. | .25 |
1/3 day mason's labor, at $2.50 per day................................ | .83 |
1/4 day helper's labor, at $1.50 per day................................ | .38 |
Total ............................................................................ | $3.34 |
Cost of stone, bluestone facing......................................... | $ .30 |
Hauling stone, say 1/10 of cost of stone............................... | .03 |
Mortar ............................................................................... | .01 |
Labor, estimating 80 sq. ft. per day for two masons and one laborer: 2 masons, at 83.00 per day.................................................. | .08 |
1 laborer, at 81.50 per day................................................... | .02 |
$ .44 | |
Cost of 1 Cubic Yard of Concrete. | |
1 bbl. of Rosendale cement, at 81.25 per bbl.................... | $1.25 |
3 bbl. of sand, or i load, at 81.50 per load......................... | .50 |
1 cu. yd. (about 6 bbl.) of broken stone, at $1.50per cu.yd. | 1.50 |
Mason, 1/4 day, at 82.50......................................................... | .63 |
Laborer, 1 day, at $1.50..................................................... | 1.50 |
Total............................................................................ | $5.38 |
Cost of 1 Square Yard of Cellar Floor. | |
Concrete, 4 1/2 in. thick, at $5.38 per cu. yd.......................... | $ .67 |
Sand bed, 6 in. thick, approximately 1 bbl............................ | .17 |
Spreading sand................................................................... | .02 |
1/12 bbl. of Portland cement for 1/2" finishing coat, at 82.60 per bbl................................................................ | .22 |
1/12 bbl. of white sand, at $1.00 per bbl................................ | .08 |
.08 | |
$1.24 | |
 