1st - When the structural steel work is up to the third tier of beams, and the walls up to the first tier of beams, stair strings started....................

2nd - When the structural steel work is up to the fifth tier of beams, walls up to the first tier of beams, and three tiers of floor arches set, and stair strings and risers set to third floor ............................

3rd - When the structural steel work is up to the seventh floor, walls up to the third floor, and five tiers of floor arches set............................

4th - When the structural steel work is up to the ninth floor, walls up to the fifth floor, and seven tiers of floor arches set .............................

5th - When the structural steel work is up to the eleventh floor, walls up to the seventh floor, and nine tiers of floor arches set, rough plumbing and heating risers up to sixth floor ............................

6th - When the building is enclosed, roof on and completed, leaders up and connected with the sewer, copings, cornices and skylights set, all floor arches set, all stair strings and risers set, and rough plumbing completed ..................................

7th - When the plumbing is complete except fixtures, steam risers and branches are all in, boilers in and set, electric tubing in and the sleepers laid in five floors

8th - When all the partitions are set throughout the building, all sleepers and fill laid, and plumbing tested to approval of the loan company..............

9th - When the brown coat of mortar is on, elevator guides set...................................

10th - When the white coat of mortar is on, jambs set, all sashes in and glazed, and the balance of the bathrooms tiled .................................

nth - When the standing trim is completed, including base, doors hung, tile in main hall and corridor set, one-half of plumbing fixtures set...................

12th - When all the finished floors are laid, doors and other trim completed, hardware on, mantels set, elevator enclosure completed, and elevators in, plumbing completed, including fixtures, smoke test made, radiators set, elevator machinery in and stair marble set.......

13th - When the building is completed, including electric light and gas fixtures, in accordance with the plans and specifications to the satisfaction of this Company and certificates issued by the Building and Tenement House Departments and Board of Underwriters........