This section is from the book "A Treatise On Architecture And Building Construction Vol4: Plumbing And Gas-Fitting, Heating And Ventilation, Painting And Decorating, Estimating And Calculating Quantities", by The Colliery Engineer Co. Also available from Amazon: A Treatise On Architecture And Building Construction.
14. The following estimates on the cost of brickwork are very carefully compiled, and will be found trustworthy. It is to be understood that the prices will vary with the cost of materials and labor; but the proportions will be constant. The figures are based on kiln, or actual, count-that is, with deductions for openings. When the work is measured with no deductions for openings, the cost per thousand may be assumed as about 15 per cent. less than the prices given, which are exclusive of builder's profit.
Cost of Common Brickwork per Thousand Brick.
Using l-to-3 Lime Mortar.
1,000 brick................... | $6.00 |
3 bu. lime, at 25 cents per bu........... | .75 |
1/2 load sand (10 bbl. to load), at $1.50 per load... | .75 |
Bricklayer, 7 hours, at 35 cents per hour...... | 2.45 |
Laborer, 7 hours, at 15 cents per hour....... | 1.05 |
Total................... | $11.00 |
Using l-to-3 Portland Cement Mortar.
1,000 brick........... | $6.00 |
1 1/2 bbl. Portland cement, at $2. 60 per bbl. ..... | 3.90 |
1/2 load sand...... | .75 |
Bricklayer, 7 hours, at 35 cents per hour...... | 2.45 |
Laborer, 7 hours, at 15 cents per hour....... | 1.05 |
Total............. | $14.15 |
Using 1-to-4. Limc-and-Cement Mortar.
1,000 brick................ | $6.00 |
3 bu.lime,at 25 cents per bu......... | .75 |
1/2 load sand........... | .75 |
1 bbl. cement............... | 2.60 |
Bricklayer, 7 hours, at 35 cents per hour...... | 2.45 |
Laborer, 7 hours, at 15 cents per hour....... | 1.05 |
Total.............. | $13.60 |
Using l-to-3 Rosendale Cement Mortar.
1,000 brick............... | $6.00 |
1 1/2- bbl. Rosendale cement, at $1.25 per bbl.... | 1.87 |
1/2- load sand............... | .75 |
Bricklayer, 7 hours, at 35 cents per hour..... | 2.45 |
Laborer, 7 hours, at 15 cents per hour....... | 1.05 |
Total.................. | $12.12 |
Cost of Pressed Brickwork per Thousand Brick.
Using Lime-Putty Mortar.
1,000 pressed brick, cost from $20 to $40 (average)........ | $30.00 |
1 1/2 bu. lime............... | .38 |
1/4 load fine sand........... | .37 |
Bricklayer, 30 hours, at 40 cents per hour...... | 12.00 |
Laborer, 15 hour,at 15 cents per hour.................. | 2.25 |
Total............... | $45,00 |
 