This section is from the book "A Treatise On Architecture And Building Construction Vol4: Plumbing And Gas-Fitting, Heating And Ventilation, Painting And Decorating, Estimating And Calculating Quantities", by The Colliery Engineer Co. Also available from Amazon: A Treatise On Architecture And Building Construction.
The cost of excavation is based on the following analysis:
Cost of 1 Cubic Yard of Excavation. | |
Cents. | |
One man can pick 15 cu. yd. per day; wages being $1.50, one yard will cost...... | |
10 | |
One man can throw out 15 cu. yd. per day; wages being $1.50, one yard will cost........ | |
10 | |
One man with horse and cart can haul on a short haul 20 cu. yd. per day; wages being $2.50, one yard will cost.................... | |
12 1/2 | |
Cost per cubic yard............ | 32 1/2 |
The cost of filling, including tamping, may be taken as about one-third that of excavation, or, say, 11 cents per cu.yd.
Summary.
Excavation, 14,216.7 cu. ft. = 526.5 cu. yd., at 32 1/2 cents per cu.yd....... | |
$171.11 | |
Filling, 747.8 cu. ft. = 27.7 cu. yd., at 11 cents per cu. yd.......... | |
3.05 | |
Total cost of excavation and filling.............. | $174.16; |
 