An interesting piece of engineering work has recently been accomplished at Bristol, England, which consisted in the moving of a foot-bridge 134 feet in length, bodily, down the river a considerable distance. The pontoons by means of which the bridge was floated to its new position consisted of four 80-ton barges, braced together so as to form one solid structure 64 feet in width, and were placed in position soon after the tide commenced to rise. At six o'clock A.M. the top of the stages, which was 24 feet above the water, touched the under part of the bridge, and in a quarter of an hour later both ends rose from their foundations. When the tide had risen 4 ft. the stage and bridge were floated to the new position, when at 8.30 the girders dropped on to their beds.
 