This section is from the book "Carpentry", by Ira Samuel Griffith. Also available from Amazon: Carpentry.
Total Building Costs By Percentages. Having carefully estimated the costs of one or two of the large items in a building, such as lumber or millwork or labor, the total cost of a building may be approximated with a fair degree of accuracy by a general contractor by means of the following table of percentages. Foundations or any other parts of a building which may be unusual should be excluded and figured separately in detail. In any event, before a building is finally completed the contractor will have to settle with each sub-contractor upon the basis of detailed cost estimates. Where time is available, the contractor as a rule secures bids from the various sub-contractors, such as the plumber, the lather, the mason, etc., combining these and adding his commission of 10% for oversight, and an additional 10% for incidentals or contingencies.
Items | Frame Building | Brick Dwelling |
Excavation, brick and cut stone...................... | 16% | 36%. |
Plastering and materials, including lathing............. | 8 | 6 |
Millwork including glass and glazing.................. | 21 | 20 |
Lumber........................................... | 19 | 12 |
Carpentry labor ........... | 18 | 10 |
Hardware......................................... | 3½ | 3 |
Tinwork and galvanized iron......................... | 2½ | 4½ |
Plumbing and gas fitting and materials................ | 7 | 3 |
Painting and materials.............................. | 5 | 5½ |
Heating (not included) | ||
Total......................................... | 100% | 100% |
Example:
A lumber bill for a given frame house is found to "figure" $500, determine the approximate cost of the various sub-contracts, and for the house as a whole.
$500 = 19% of the total cost. | ||
Total cost = $2632 (exclusive of heating). | ||
Excavation, brick and cement work = 16% of $2632 | = | $421.12 |
Plastering = 8% of $2632.................................... | = | 210.56 |
Millwork and glazing = 21% of $2632........................ | = | 552.72 |
Carpentry labor = 18% of $2632............................. | .= | 473.76 |
Hardware=3½% of $2632.................................. | = | 92.12 |
Tinwork = 2½% of $2632................................... | = | 65.80 |
Plumbing = 7% of $2632.................................... | SB | 184.24 |
Painting = 5% of $2632...................................... | = | 131.60 |
Lumber...................... | = | 500.00 |
$2631.92 | ||
To this must be added heating, electric wiring, electric and gas fixtures, window shades, cement walks, sewerage, grading, decoration of walls, architect's fee and contractor's commission.
For furnace heat, add 6 to 7%; for steam, add 8 to 10%; for hot water, add 10 to 12% additional.
For electric wiring, add 1¼%- For fixtures, electric and gas, add 2 to 3%.
To this total add 10% for incidentals and contingencies; add 10% for contractor's charge. Above this amount add 6% for architect's fee, to get the cost to the owner.
Such a method of estimating should not be mistaken for anything but fairly safe approximation where normal conditions exist.
 
Continue to: